CASE STUDY - Pottsville Holiday Park Foreshore
Onsite Construction - 6 days for 113 lineal metres at 1.8mt highSevere continual erosion and loss of land at the caravan park due to tidal serges and rain.
Council was continually filling behind the wall due to erosion. This was dangerous for families that were trying to access the beach. Gabi Block has created an impressive wall edge to the river and this lovely park area. Our Construction Process...• Demolish old inadequate timber retaining wall
• Dig and construct a concrete footing, lay Geofabric • Place base course of blocks onto footing. • Following day, continue laying blocks, pulling up Geofabric and backfilling and compaction. Lay turf. • Fence completed by council |