CASE STUDY - Mountain Creek Fire Trail Road Support
Onsite Construction - 4 days start to finishThe problem the council was facing here is a road needed to be built for a fire trail, the existing batter slope was unsuitable to get a fire truck along past the creek and to the back of the houses. Due the access to the site being very limited, other methods were not suitable for this project.
Our Construction Process...* Poured footing
* Layed Geofabric * Base course blocks laid on footing * Following day continued building wall * Geofabric then pulled up the back of the wall and back filled and compacted as job progresses * On 4th day, topsoiled, seeded and fence put in place and grouted |