CASE STUDY - Bardon Land Slip and Drainage
Onsite Construction - 4 1/2 days start to finishThe project we see here has a severe under ground water problem. Because of the road being directly above the job, construction time was crucial. With the excavation being left open for so long there were grave concerns of the possibility of a land slip. Other traditional methods were quoted at 6 ½ weeks construction time.
Our company, using Gabi Products was chosen due to it its high drainage capabilities, on site construction time and architecturally finished product. Our Construction Process...* Keyway footing dug
* Geofabric laid * Base course of blocks laid on footing * Following day blocks were laid up the wall * Geofabric pulled up behind the wall and back filled * Compacted as job progresses * Post hole inserts are already within the blocks * Safety fence prefabricated and dropped into place and then grouted * On site construction time- 4 ½ days start to finish |